Other projects

 

  1. Three Transmission Gas Pipelines and Two City Gas Distribution Networks Project: ACESCo provided basic design and tender documents for the construction of the following Four Transmission Pipelines & Two area distribution networks:

     

    • Transmission Gas Pipe Line Benghazi-Tobruk with total length of 450Km
    • Transmission Gas Pipe Line AlWafa-Sabha with total length of 480Km
    • Transmission Gas Pipe Line Entessar Field 103-Sarir with total length of 250km
    • Transmission Gas Pipe Line Nalut-Gherian with total length of 200km
    • 4 Cities Gas Distribution Network in Green Mountain Area  
    • 3 Cities Gas Distribution Network in Western Mountain Area
  2.  

  3. Gas Master Plan and City Gas Distribution Networks Project
  4. For Gas Master Plan ACESCo provided the following:

    • Optimized investments in gas transmission pipelines in the long term
    • Study the feasibility and basic design of pipeline infrastructure and city gas distribution
    • Optimum routes for gas transmission by accommodating future needs for power & industrial sectors, and domestic consumption
    • A set of studies for the project implementation

     

    For City Gas Distribution Networks ACESCo provided basic design and tender documents for projects construction (Transmission and Distribution Projects) to feed 500,000 Domestic & commercial customers located in the following areas:

    • Tripoli, Misurata., Benghazi
    • Al Azizia, Al Nawahi Al Arbaa, Tajura, West Janzor
Azzawia, Sorman , Sabratha, Zwara , Misullatah, El Khoms, Zletin